Homeowner's Refusal to Make One Payment in a Construction Installment Contract Constitutes a Substantial Breach of the Contract
The South Carolina Court of Appeals recently decided that a homeowner's refusal to make an installment under construction contract constituted a substantial breach of the contract. See Silver v. Aabstract Pools, 376 S.C. 585, 658 S.E.2d 539 (Ct. App. 2008).
A homeowner and contractor contracted for the construction and installation of an in-ground swimming pool. The contract called for five payments upon the completion of five scheduled tasks. The homeowner made three of the payments according to the schedule, however, the homeowner refused to make the fourth payment because he opined that the job was only approximately 20% complete and the payment schedule did not correlate with the progress of the job. The case was heard by the Master-in-Equity who determined the contractor had breached the contract when the contractor ceased work on the project and removed his equipment because the plaintiff refused to make the required payment. The contractor appealed the decision and the Appellate Court found in his favor. The court held that the contract was clear and unambiguous. Furthermore, the court refused to look beyond the four corners of the contract to determine its meaning. The homeowner could not change the agreed upon terms in midstream because he was unhappy with them. The court found no evidence that the contractor had breached the contract, and since the homeowner’s refusal to pay was a substantial breach of the contract, the contractor had the right to cease work and recover the value of work already performed. As the first party to breach, the homeowner must bear the liability of his nonperformance. The court awarded the contractor damages for the nonperformance, attorneys’ fees, and court costs.
This site and any information contained herein is intended for informational purposes only and should not be construed as legal advice. Seek a competent attorney for advice on any legal matter.
Related Links
Adjust Text Size
Subscribe to Contactor Headlines
Categories
-
- BIM
- Best-Practices
- Career
- Codes-Standards
- Construction-Accounting
- Construction-Books
- Construction-Equipment
- Construction-Events
- Construction-Law
- Construction-News
- Construction-Productivity
- Construction-Products
- Construction-Safety
- Construction-Technolgy
- Construction-Technology
- Construction-Training
- Construction-Workforce
- Customer-Satisfaction
- Customer-Service
- Design-Engineering
- Entrepreneurship
- Estimating
- Green-Construction
- Industry-Association
- Industry-Outlook
- Interesting
- Leadership
- Lean-Construction
- Management
- Operations
- Organizational-Change
- Outside-The-Box
- Personal-Productivity
- Process-Documentation
- Project-Delivery
- Project-Management
- Public-Works
- Risk-Insurance
- Sales-Marketing
- Strategy
- Studies-Lists
- Talent
Pre-Planning Facilitation
Improve Profitability On Your Next Project
Archives
Favorite Book 2007
The Toyota Way is my favorite book for 2007. It had so many good ideas that I could not keep up and ended up reading it again and even buying the Field Book to go along with it.
Download Elegant Solutions from Change This which provides some highlights of the Toyota Production System. Too many ideas that are applicable to contractors to even count!
Recent Posts
-
- Works stops on Olympic Stadium
- Construction Estimating Software Study
- The Best Industry in the United States
- Welcome
- 2,300 construction jobs slashed in two days
- ODA to beef up Olympic Park security
- Taylor Wimpey wins design award
- Chris Hobbs of CADline has written an interesting article about the industry take-up of Building Information Modelling (BIM) technology
- Homeowner's Refusal to Make One Payment in a Construction Installment Contract Constitutes a Substantial Breach of the Contract
- Planning delays already predicted for proposed eco-towns
Management Class Series
Training Modules Specifically Designed For Contractors- Construction Documentation Overview
- Scheduling
- Project Pre-Planning Impacted Jobsite Productivity
- Production Tracking Customer Service & The Project Team
- Change Orders Talent - “People Processes”
- Profit Dynamics For Construction Contracts
- Cash Flow & The Project Team
- Priorities (Time Management For Construction)
- Construction Financial Basics
- Integrated Accounting & Operations
- Project Management Overview
- Process Documentation
- Effective Superintendent Processes
- Implementing A Project Management System
- Organizational Planning For Contractors
- Technology Systems For Contractors
- Excel for Contractors